Name: Riabovskiy Ceramic Plant
Address: Leningrad region, Tosno district, Ryabovo
Executed works: working out of designs and shop drawings of power supply system, internal and external lighting system, power equipment system, TV system, sound system, broadcasting, BMS, telephone network
Status: works completed
Period of works: March 2009 - December 2010
Project managers: Ezhova D.Y., Lebedev M.S., Verteletsky I.V., Plohih M.I., Nekrasov R.A., Bogachkov D.A.
Executed works: installation of external lighting system, internal and power equipment system of main production and utility buildings, power supply system 10 kV
Status: works completed
Period of works: June 2010 – December 2011
Project managers: Butakov A.S., Chertopalov V.P., Starovoit A.V., Karpovich V.M., Zagorovskiy Y.V.
Executed works: working out of designs and shop drawings of power supply system 10 kV
Status: works completed
Period of works: August - December 2010
Project managers: Ezhova D.Y., Koval A.P.
Executed works: installation of power supply system 4 kV, of temporary covered warehouse and lighting of open warehouse
Status: works completed
Period of works: July - August 2010
Project managers: Chertopalov V.P., Smetanin A.V., Karpovich V.M.
Executed works: installation of temporary power supply system and lighting system of main production building
Status: works completed
Period of works: August – September 2010
Project managers: Butakov A.S., Chertopalov V.P., Smetanin A.V., Karpovich V.M.
Executed works: installation of cable canalization for 4 kV network of weak current system
Status: works completed
Period of works: August 2010 – December 2011
Project managers: Chertopalov V.P., Starovoit A.V., Zagorovskiy Y.V.